The minimum stagger for hardwood flooring should be three times a board width.
Staggered siding joints.
End joints of the individual panels are staggered for appearance and to a lesser degree staggering the joints adds some minor strength to the overall installation having all joints.
Install succeeding courses similarly.
Butt joints in adjacent courses should be spaced apart by at least two stud bays for 16 inch o c.
It s best to stagger the joints in each successive course to avoid noticeable patterns.
Plan overlaps where they ll be the least visible and stagger joints at least 2 feet from course to course which will add to the siding s stability.
Condition correction lap siding nailing self aligning lap siding nailing vertically aligned joints staggered joints flashing apply siding over approved structural sheathing.
Stagger the end joints of subflooring siding and wood floor coverings both for stability and appearance.
Some will stair step it others alternate the lap up the wall.
Different siders do it different.
James har lap siding installation joint flashing laps seams vinyl staggered shake siding foundry 10 tips for installing vinyl siding pro construction guide 13 simple vinyl siding installation tips the family handyman 13 simple vinyl siding installation tips the family handyman hartford ct seamless vinyl siding peter l brown company.
Mark the slope with a pencil on the short piece of siding.
Framing or one bay for 24 inch o c.
Install the first panel by pushing the panel s buttlock up into the locking tab on the starter strip.
Maximum nail spacing is 16 in.
Hold a second piece of siding against the j channel at the slope of the gable.
With time you will figure out what looks good and does not waste anymore material then needed.
How to stagger vinyl siding joints.
Stagger end laps so that one is not directly above the other unless separated by three courses.
Remove the short piece and cut along the pencil line as a pattern for the gable angle cuts.
Here bob vila describes a way to get started that will ensure staggered joints every time.
Install additional courses of siding.
For laminate flooring it s more like 12 inches.
The siding laps should be staggered.
Lock a short piece of siding into the gable starter course i e the last course before the gable starts.
Nails must penetrate wood framing 1 1 2 in.
Lay out the panels required for the first course along the house.
When a stagger is visible it s best to keep the pattern random.
For walls longer than 12 feet you ll need to butt additional lengths of siding together.
Cut the panels to length with tin snips.